Our 12 Impacts / Waste and Resource Use / Performance 2007
The amount of coal burned in our power station was 22% lower this year and gas use was 19% higher
Waste volumes increased due to power station refurbishment and construction
![]()
Internal electricity use was more than 35% lower, due to a reduction in power station works power
EnergyNetworks pioneered a new, safe oil sampling technique, reducing the volume of transformer oil used and sent for recycling
![]()
Rye House Power Station’s rainwater harvesting scheme was recognised in the Environment Agency’s annual report as an example of best practice
![]()
The volume of ash recovered for use in construction products increased by more than 45% on the previous reporting period, to more than 580,000 tonnes
![]()
ScotAsh, our joint venture with Lafarge Cement, sold a record 1.1 million tonnes of construction products manufactured from Longannet and Cockenzie power stations’ ash
Key Waste and Resource Use measures summarised in the table below.
| 2007 | 2006/07 | ||
|---|---|---|---|
| Coal (‘000 tonnes) | 5,190 | 6,682 | |
| Oil (‘000 tonnes) | 10 | 10 | |
| Gas (‘000 tonnes) | 1,716 | 1,447 | |
| Biomass & WDF (‘000 tonnes) | 110 | 126 | |
| Internal Energy - electricity (GWh) | 874 | 1,361 | |
| Townswater (million m3) | 5 | 3.63* | |
| PFA ash by-product reused ('000 tonnes) | 583 | 400 | |
| FFC oil containment losses (litres) | 17,107 | 15,711 | |
| *townswater usage was under reported because Cockenzie had not reported water usage from the coal plant. This was spotted in the external data audit commissioned at the site this year. | |||
We use significant volumes of primary resources to generate electricity and supply gas to our customers, including more than five million tonnes of coal and nearly two million tonnes of natural gas.
The amount of coal burned in our power station was 22% lower this year and gas use was 19% higher. This was due to the collapse of a coal conveyor at Longannet in January 2007 which meant that the station was unable to burn coal for six weeks while remedial action was taken. During this outage, gas, which is normally only used for start up and shut down at Longannet, was used to operate Units 1 and 3 with a reduced load.
In 2006, the amount of coal used in generation was particularly high due to reduced out put from Scotland’s nuclear stations, sustained high gas prices which made coal more economically favourable, and outages at Shoreham.
We also use oil for power station start-up and in electrical equipment, such as transformers.
Most of the townswater we consume is process water, which is converted into steam in the power station boilers to generate electricity. We also abstract significant volumes of water from the River Forth to be used as cooling water at Longannet and Cockenzie power stations. This is returned to the estuary after use.
The volume of resources we use and the amount of waste we produce depends on the number of large capital projects we are undertaking and varies from year to year. We place great emphasis on reducing, reusing and recycling resources in all our day-to-day processes and major projects.
This year we have started reporting our wastes in line with the European Waste Catalogue classifications, to be consistent with our regulatory reporting arrangements and with future reporting as part of the wider IBERDROLA Group.
| Performance Targets 2007 | Outcome |
|---|---|
| Embed updated environmental KPIs into business unit scorecards to enhance governance and environmental performance | Energy Wholesale reports monthly on 15 environmental KPIs and progress to complete key environmental plan targets. EnergyNetworks compiled a KPI template for business reporting, implementation has commenced |
| Implement revised policies on Transport and Internal Resource Use (energy, water, waste) | Ongoing |
| Update the integrated environmental performance and reporting criteria into the selected contracts within our EnergyNetworks business | EnergyNetworks have developed waste measures as part of their KPI matrix. Future waste and scrap contracts will include waste reporting criteria. |
| Review depot waste stream segregation in our EnergyNetworks business to maximise waste recovery and recycling activities | Internal audit reviews over many years have demonstrated that segregation of wastes could be better. We have directed the prospective future tender contractors to our desire for greater segregation in provision. We have Identified a voluntary sector service provider for Resin bucket recycling this is still under consideration. We have completed renewal of scrap contracts including refreshment of SF6 recovery and reporting to integrate new FGas regs. We have briefed the business on the new statutory requirement for SF6 recovery |
| To undertake waste minimisation reviews for PPC permitted sites within our Energy Wholesale business | Water and waste minimisation audits have been completed at all sites not just PPC ones |
- Complete energy minimisation audits at PPC permitted sites within our Energy Wholesale business
- Implement new waste contract arrangements (SWmps) in our EnergyNetworks business
Resource Use
During 2007 we carried out several major capital projects in Energy Wholesale, EnergyNetworks and ScottishPower Renewable Energy that used significant quantities of materials, including steel.
These projects included the development of new onshore windfarms and environmental investments at our power stations, including Flue Gas Desulphurisation at Longannet and a project to replace more than 20 tonnes of reinforced glass panelling at Cockenzie.
EnergyNetworks are conducting a series of network reinforcements to enable electricity from new renewable energy projects to be transported to where it is needed. The construction of new power lines and substations involves using large quantities of metal, including steel and copper. The business has also carried out significant refurbishment of the distribution network to improve the security of supply in rural areas.
Serving 5.23 million customers, Energy Retail uses a significant volume of paper in customer billing and communication. In recent years, the amount of paper used has reduced due to streamlining the bill, and the increase in the number of customers who manage their accounts online - now around 12%.
Reduce
- Cockenzie Power Station has reduced the amount of carbon in ash (the amount of unburnt carbon lost from the combustion process) from 15% to 7% as a result of an overhaul of most of the station’s pulverizing mills, airflow optimisation and development of an automatic control strategy. The improvements have reduced the use of fuel and works energy, and the volume of ash disposed of to settling lagoons
- A Business Transformation project implemented by Energy Retail’s Customer Establishment has looked at ways of reducing paper consumption, including e-mail communication with customers, and setting targets for waste minimisation
- ScottishPower Renewable Energy’s new Black Law extranet allows Habitat Management Groups and external stakeholders to access a wide range of documentation and reports on habitat management objectives and surveys at Black Law and other windfarms online. The extranet is one way we are disseminating information in an environmentally sensitive manner by reducing paper usage
- Since March 2007, coal deliveries to Longannet have been completed almost exclusively by freight train. Up to 10 coal train loads are delivered to the station per day from Hunterston, with approximately 1,000 tonnes arriving with each delivery – that’s the equivalent of taking more than 30 fully-laden lorries off Scotland’s roads per delivery
- A project team involved in reinstating the seawall at Longannet’s Valleyfield Lagoon No.5 sourced 15,000 tonnes of Grade 1 Armour stone from a local quarry at Inverkeithing, considerably reducing the carbon miles involved in transporting 800 lorry loads of aggregate
- EnergyNetworks pioneered a new, safe method of sampling transformer oil, which enables oil to be tested to assess its condition. Previously, transformer oil would have been replaced according to the length of time it had been inside the transformer, regardless of its condition. The new testing process will result in transformer oil being replaced only if there is a need to, thus reducing the amount of oil used
- EnergyNetworks is significantly reducing the environmental impact of its cable laying processes through the use of ploughing methodologies that allow cable to be inserted underground with little or no excavation. The ‘mole plough’ system is quicker to operate, causes minimal disruption and does not produce spoil that has to be disposed of to landfill
Reuse
- ScotAsh, the company’s joint venture with Lafarge Cement, reuses the ash output from Longannet and Cockenzie power stations in environmentally friendly construction products, including grouts and cements. During the year ash reuse increased by around 45% and ScotAsh achieved record product sales of 1.1 million tonnes. The company supplied several high profile projects during 2007 including cement for the turbine bases at Whitelee Windfarm, the new Upper Forth Crossing, the shaft isolation project at the Atomic Energy Authority’s Dounreay plant in Caithness and Scottish and Southern Energy’s Glendoe hydro project. ScotAsh was named as National Example of Excellence in Business in the Community’s TCS Marketplace Innovation Award 2007
- A rainwater harvesting project implemented at Rye House Power Station during 2007 should result in a 25% reduction in townswater usage. Previously, all run-off rainwater from buildings and roads was collected in an underground retention reservoir before being discharged into the River Lea. The £100,000 project is now recovering this relatively clean water and treating it by means of a gravel/sand filter plant. The filtered water is then reused for plant processes instead of using townswater from the mains supply. The project was recognised in the Environment Agency’s annual report as an example of best practice
- While awaiting the completion of a new, purpose-built biomass plant at Longannet, we continued to co-fire Waste Derived Fuel from SMW Limited’s sludge drying facility near Glasgow, recovering useful energy. We also co-fire biomass fuels, including sawdust and peanut husks at Longannet and Cockenzie power stations
- Longannet’s Stores Team took delivery of a quantity of plastic pallets. These heavy-duty plastic pallets have a lifespan of around 10 to 15 years which will reduce the station’s consumption of standard wooden pallets
Recycling
- A project team from EnergyNetworks identified recycling opportunities during the refurbishment of the Capenhurst ‘A’ 132 kV sub station. Demolition rubble was crushed on site to be used as a structural backfill layer for new foundations, also reducing transport and landfill costs, and the need to import new aggregates. Meanwhile, redundant cables were recycled and timber packaging was reused to store strategic spares at a nearby sub station
- In September 2007, Longannet conducted trials involving the recycling of marine debris that is gathered by the cooling water drum screen trash basket. As an alternative to disposal via landfill, this waste was collected by CEG of Auchterarder, to be composted for eventual use as a growing medium in gardens
- ScotAsh, our joint venture with Lafarge Cement, supplied products made from power station ash to a sustainable roads project led by City of Edinburgh Council. ScotAsh’s RSA/PT product is milled with road planings to stabilise it and enable it to be reused in road reconstruction instead of landfilled. The company also supplied its bedding mortar and joint filling grout to several local authorities. This enables setted roadways to be repaired using the original stone setts
UK general waste data*
| 2007 | 2006/07 | |
|---|---|---|
EU Waste Categorisation |
||
| 07 Wastes from organic chemical process | ||
| Hazardous waste arising (tonnes) | 0.76 |
0.28 |
| 08 Wastes from MFSU of coatings, adhesives, sealants and printing inks | ||
| Hazardous waste arising (tonnes) | 1.96 |
0.23 |
| 13 Oil waste and wastes of liquid fuels | ||
| Hazardous waste arising (tonnes) | 1,246 |
12,183 |
| Hazardous waste recovered (tonnes) | 1,041 |
11,598 |
| 15 Waste packaging | ||
| Hazardous waste arising (tonnes) | 4.26 |
|
| Non hazardous waste arising (tonnes) | 3.49 |
0.01 |
| Non hazardous waste recovered (tonnes) | 1.3 |
|
| 16 Waste not otherwise specified in the list | ||
| Hazardous waste arising (tonnes) | 1,428.33 |
38.12 |
| Hazardous waste recovered (tonnes) | 1,427.22 |
38.12 |
| Non hazardous waste arising (tonnes) | 476.04 |
778 |
| Non hazardous waste recovered (tonnes) | 476.04 |
778 |
| 17 Construction and demolition wastes | ||
| Hazardous waste arising (tonnes) | 477.51 |
|
| Hazardous waste recovered (tonnes) | 473.5 |
|
| Non hazardous waste arising (tonnes) | 233,812 |
259,073 |
| Non hazardous waste recovered (tonnes) | 233,812 |
|
| 20 Municipal wastes (household and similar commercial and industrial) ** | ||
| Hazardous waste arising (tonnes) | 124,454 |
36,204 |
| Hazardous waste arising (litres) | 560,576 |
79,905 |
| Hazardous waste recovered (tonnes) | 12.35 |
2,010 |
| Hazardous waste recovered (litres) | 210.565 |
83 |
| Non hazardous waste arising (tonnes) | 27,469 |
8,088 |
| Non hazardous waste arising (litres) | 64,627 |
414,384 |
| Non hazardous waste recovered (tonnes) | 6,933 |
1,330 |
| Non hazardous waste recovered (litres) | - |
|
| IT equipment (recycled tonnes) | 34 |
24 |
| IT equipment (recovered for use - items) | 1,548 |
855 |
| *These figures do not include data from Core or waste arising from windfarm development programme | ||
| **Includes waste from power station refurbishment and construction projects. | ||
Generation (UK) Ash Data |
2007 | 2006/07 | ||
|---|---|---|---|---|
| Non hazardous ash arising (tonnes) | ||||
FBA from Longannet and Cockenzie |
73,226 |
79,549 |
||
PFA Cockenzie |
274,685 |
234,537 |
||
PFA Longannet |
325,471 |
445,446 |
||
PFA total |
600,156 |
679,983 |
||
| Ash recovered for sale (tonnes) | ||||
FBA from Longannet and Cockenzie |
67,446 |
79,549 |
||
PFA Cockenzie |
343,960 |
269,552 |
||
PFA Longannet |
238,720 |
130,144 |
||
PFA total |
582,680 |
399,696 |
||
| Net disposal of ash (tonnes) | ||||
FBA from Longannet and Cockenzie |
5,780 |
- |
||
PFA Cockenzie |
-69,275 |
-35,015 |
||
PFA Longannet |
86,751 |
315,302 |
||
PFA Total |
17,476 |
280,287 |
||
| FBA - Furnace Bottom Ash | ||||
| PFA - Pulverised Fuel Ash | ||||
| SF6 releases and quantities held | 2007 | 2006/07 |
|---|---|---|
| Total UK quantity held (tonnes) | 92 | 80 |
| Total UK number of switchgear units holding SF6 | 22,116 | 21,036 |
| Total UK quantity of SF6 released (tonnes) | 0.46 | 0.40 |
| Total UK quantity of SF6 recycled / reused (tonnes) | 0.276 | 0.154 |
| Contaminated land site review | 2007 | 2006/07 |
|---|---|---|
| Phase I surveys | 2 | 58 |
| Phase II surveys | 2 | 4 |
| Remediation expenditure | £11,726 | 0 |
| Oil Containment | 2007 | 2006/07 |
|---|---|---|
| FFC Oil losses from underground cables | ||
| Litres lost | 17,107 | 15,711 |
| Transformer & switchgear oil containment data | ||
| Total volume of oil held (litres) | 91,917,505 | 92,195,410 |
| Volume of oil lost (litres) | 45,070 | 33,097 |
| Total number of transformers bunded to date | 454 | 444 |
| Anual investment in bunding (£'000) | 223 | 91 |
| PCB status of equipment | 2007 | 2006/07 |
|---|---|---|
| Number of samples tested - We currently have no programme to test equipment. Issues will be managed if they arise. | 0 | 0 |
| Number of samples above 50 ppm | 0 | 0 |
| % equipment now tested for PCB levels (Ground mounted equipment) | 100 | 100 |
| UK resource use total | 2007 | 2006 |
|---|---|---|
| Coal burn ('000 tonnes) | 5,190 | 6,682 |
| Oil burn ('000 tonnes) | 10 | 10 |
| Gas burn ('000 tonnes) | 1,716 | 1,447 |
| Townswater water use (million m3) | 5 | 3.63* |
| Tidal/river/bore hole water use (million m3) | 1,882 | 2,463 |
| Biomass and WDF (‘000 tonnes) | 110 | 126 |
| *townswater usage was under reported because Cockenzie had not reported water usage from the coal plant. This was spotted in the external data audit commissioned at the site this year. | ||
| Total business mileage | 2007 | 2006/07 |
|---|---|---|
| UK businesses | 17,597,999 | 17,902,433 |
| Vehicle Fuel Consumption for Main Group Fleets (estimated figures) | ||
| Volume of petrol used ('000 litres) | 461 | 138 |
| Volume of diesel used ('000 litres) | 5,901 | 6,613 |
| Volume of Liquified Petroleum Gas (LPG) used ('000 litres) | 14 | 3 |
| Internal energy use | 2007 | 2006/07 |
|---|---|---|
| UK businesses | ||
| Electricity (GWh) | 874 | 1,361 |
| Gas (GWh) | 4 | 156 |
| Gas/diesel oil (litres) | 143,819* | 146,568* |
| *this is diesel used in generators only. CO2 has been accounted for in EU ETS CO2 total. | ||
